For the connection to the central wastewater treatment plant on the Vltava River island Císařský in Prague, a pipeline was installed using the HDD method beneath the Vltava. Tight bending radii made pipe pulling difficult, and the geological conditions were unstable due to shale rock. Therefore, an integrity test was required to verify the integrity of the new pipeline after installation. The egeplast SLM® DCT (Detection and Checking Technology) pipe system was used for this purpose.

Connection of a Wastewater Treatment Plant
The connection of the Podbabsk wastewater treatment plant in Prague to the central treatment plant on the Vltava River island Císařský presented major challenges for the general contractor ZEPRIS. To increase transport capacity, a double pipeline with dimensions of 400 x 23.7 mm was installed, along with five manhole structures on the island. The total length of the pipe string is approximately 1,050 m. The trenchless sections crossed beneath the Vltava as well as old tree growth along the river bank.
The trenchless installation using the HDD method beneath the Vltava riverbed was carried out by TALPA-RPF. The start and end points of the river crossing were already predetermined by the connection points of the original pipeline. Due to these fixed points, a relatively short distance, and the resulting tight bending radius, the drilling was demanding. The pilot drilling was also a major challenge, particularly on the bank side. Due to the shale rock in the area of the drill channel, the geological conditions were unstable and could have caused difficulties in the area of the borehole during pipe pulling. Due to the longitudinal profile of the siphon and the very demanding geology of the subsurface, the SLM® DCT pipe was therefore selected, which enables an integrity test directly following installation.

After 18 days, the reaming of the two 160 m long pipe strings beneath the Vltava was completed. During technical monitoring of the construction, the operator was able to verify the quality of the installation and the integrity of the installed pipelines multiple times. The design office was able to successfully prepare the project documentation.
“We used the system that enables inspection of PE pipes after installation for the first time. However, the positive experience will certainly lead to further use in our trenchless construction projects,” explains Ivan Demjan, Managing Director of TALPA-RPF s.r.o.
Project Description
Connection of a wastewater treatment plant to the central treatment plant on an island
Challenges
Tight bending radii and unstable geological conditions due to shale rock
Solution
Verification of the integrity of the new pipeline after trenchless pipe pulling under difficult conditions
Pipe System
1,050 m SLM® DCT for pressurized wastewater; dimensions: 400 x 23.7 mm
Project Participants
General contractor: ZEPRIS s.r.o., Prague
Reaming: TALPA-RPF s.r.o., Ostrava
Project documentation: D-PLUS
egeplast
SLM® DCT
Verification of the pipe system’s integrity for construction performance acceptance
Increased operational safety
permanent Localization Capability
Trenchless installation techniques are possible without life-shortening damage or reduction of the safety factor.



