The relining method ensures a future-proofed supply infrastructure
By rehabilitating the Lorenzer downpipe line, N-ERGIE Netz GmbH invested in the long-term security of Nuremberg’s drinking water supply. Over a length of around 1.7 km, an existing cast-iron pipeline DN 550 was renewed using an egeplast egelen® PE pipe system. The trenchless relining method made it possible to continue using the existing route. This method shortens construction times, reduces interventions in the traffic area, and conserves resources.

Renewal in an inner-city environment
The existing drinking water transmission pipeline runs through a densely built-up urban area, meaning that conventional replacement would have required extensive civil engineering work and would have significantly impacted traffic and local residents.
The aim of the project was therefore to renew the pipeline sustainably while minimising interventions in the existing infrastructure.

The new PE-HD pipe is pulled into the existing cast-iron pipeline using the relining method.

Positioning of the pipe string for the trenchless rehabilitation of the drinking water pipeline.

The pre-welded pipe string was laid out along the existing route for insertion.
Trenchless rehabilitation over around 1.7 km
An egeplast egelen® PE-HD pipe 500 × 45.5 mm was used for the rehabilitation. The entire pipeline was renewed in five construction sections using trenchless relining with the PE reduction method.
In this process, the new pipe’s outside diameter is reduced before insertion and then pulled into the existing cast-iron pipeline using a hydraulic cable winch system. After installation, the pipe returns to its original geometry and forms a new, permanently high-performance drinking water pipeline inside the old line. The existing route can continue to be used, while construction activity is limited to a few excavation pits.

Less civil engineering work, greater future-proofing
The trenchless construction method avoided extensive earthworks. At the same time, traffic areas, surface pavements, and existing infrastructure are subjected to significantly less strain than with complete replacement.
By using the egelen® pipe system, the network operator and the people of Nuremberg gained a modern drinking water pipeline designed to meet the requirements of a long-term secure supply.

Project Description
Rehabilitation of a drinking water transmission pipeline in Nuremberg
Challenges
Inner-city location, minimal interventions in existing infrastructure
Solution
Trenchless relining using the PE reduction method
Installation
1.7 km in five construction sections
Pipe System
egeplast egelen® PE-HD 500 × 45.5 mm
Project Participants
N-ERGIE Netz GmbH, Pfaffinger Bau SE from Passau in cooperation with the Berlin-Brandenburg branch