Safe Industrial Wastewater Disposal

The Austrian industrial company AGRANA, with a facility in Aschach an der Donau, planned a wastewater pipeline that runs through a water protection zone. Since it had to be permanently monitored and pressure-tight, the egeSmart:Leak Control 3L was deployed.

At the Aschach industrial site, AGRANA refines the natural raw material corn into high-quality starch-based products. For a new disposal pipeline in a drinking water protection zone, a fully monitored pipe system with permeation protection was selected in consultation with the Upper Austrian State Government—pressure-tight and with an outer diameter of OD 630 mm.

Over a length of 170 m, the egeSmart:Leak Control 3L with electronic leak monitoring was installed. This system enables permanent monitoring of the pipeline section in the drinking water protection zone. For this purpose, the electrically conductive intermediate layer made of aluminum is permanently subjected to a low voltage. The resistance of the integrated aluminum layer is then monitored by a grounded monitoring unit. An alarm is triggered even in the event of minor damage. The signal can also be transmitted via GSM and used to shut down the pipeline. The system also enables precise location of a damage point.

The entire civil engineering work was carried out by the construction company Weber Bau GmbH from Rohrbach, Austria. In the drinking water protection zone, both the excavation work and the handling of heavy welding equipment were performed with care. The pipe ends of the 12-meter sections were butt-welded. After each weld, the conductivity was checked. After completion of the entire pipe section, the function was tested from beginning to end using a control cable and connected to the monitoring system.

Project Description

Wastewater pipeline through a water protection area

Challenges

Pipeline must be permanently monitored and pressure-tight

Solution

Installation of a disposal pipeline OD 630 mm with a length of 700 m in several sections, of which 170 m are fully monitored

Installation

Open construction, in open trench

Pipe System

egeSmart:Leak Control 3L
OD 630 mm SDR 17

Project Participants

Client: AGRANA Austria
Installation: Weber Bau GmbH, Rohrbach

egeplast
egeSmart:Leak Control 3L

Permanently monitored pipe system that detects and reports damage.

Permeation-resistant pipe system

Pipe location

Permanent leakage monitoring

SMS signal

Forwarding of messages to a control center

Remote monitoring

Location of damage

Learn more
Your Contact
Dipl.-Ing. Dirk den Ouden
Head of Applications Engineering, egeplast international GmbH

Suez Eau France renovates drinking water pipeline with SLM® in Bordeaux

Read more

SLA® Barrier Pipe meets the highest requirements in contaminated soils

Read more
Unlock All Downloads
Thank you for your interest! Please complete the fields to instantly access this and all future downloads from our site.