With the phase-out of lignite mining, drinking water supply in the Lusatian mining region is facing profound change. To ensure a mining-independent supply in the long term, ewag kamenz is modernising a section of the “Inner Ring” long-distance drinking water pipeline.
Through sensitive nature conservation areas, installation was carried out primarily by relining – with integrity verification and permanent locatability of the pipeline.

Future-proofed drinking water infrastructure for structural change
The “Inner Ring” long-distance drinking water pipeline operated by ewag kamenz forms one of two central north–south axes in the Lusatian mining region drinking water network. The approximately 12 km-long pipeline runs from Bernsdorf via Lauta to Großkoschen, crossing the state border between Saxony and Brandenburg.
In the first construction phase, an approx. 3,800 m section of pipeline between Lauta-Dorf and the Johannisthal structure will be renewed. The aim of the measure is to increase the flexibility of the interconnected network, support regional development in the supply area of ewag kamenz—particularly in the Lauta–Hoyerswerda area and the Lusatian Lake District—and sustainably expand pumping and transfer capacities.
For the renewal of this pipeline, the pipe insertion method (relining) was selected, particularly to achieve an economical construction approach. The challenge was the small annular space between the existing DN 600 steel pipeline and the new DN 500 pipeline, which was further reduced by heavy encrustations in the existing pipeline. To create sufficient reserves for insertion, it was intended to dispense with sliding skids. However, this required reliable verification of the integrity of the carrier pipe after insertion.

The integrity test provides verification of damage-free installation following trenchless installation.

Pre-assembled pipe strings for insertion into the existing “Inner Ring” long-distance drinking water pipeline.
Clear verification of damage-free installation with egeplast SLM® DCT
The egeplast SLM® DCT pipe system was used for the modernisation. The new drinking water pipeline was implemented in the dimension 500 × 29.7 mm (SDR 17).
The electrical conductor tapes integrated in a spiral beneath the protective jacket enable the pipe system to be tested for integrity directly after installation. The pipe system also offers the option of permanently locating the installed pipeline.
Cost-effective renewal with minimal intervention
The renewal was carried out predominantly trenchlessly using long-pipe relining. Only in certain sections were route adjustments in open-cut construction required to ensure accessibility for future maintenance work.


Project Description
Modernisation of the “Inner Ring” long-distance drinking water pipeline in the Lusatia drinking water network
Challenges
Small annular space between old and new pipe, as well as heavy encrustations in the existing pipeline
Solution
Use of egeplast SLM® DCT with integrity verification after pipe insertion
Installation
3,620 m relining, 265 m open-cut construction
Pipe System
egeplast SLM® DCT drinking water pressure pipe 500 × 29.7 SDR 17
Project Participants
Client: ewag kamenz – Energie und Wasserversorgung Aktiengesellschaft Kamenz
Design: DWG Planung und Beratung GmbH
Execution: TrappInfra Rohrbau Welzow GmbH
egeplast
SLM® DCT
Verification of the pipe system’s integrity for construction performance acceptance
Increased operational safety
permanent Localization Capability
Trenchless installation techniques are possible without life-shortening damage or reduction of the safety factor.