The SuedLink grid expansion project is creating one of Germany’s most important power connections. As a high-performance high-voltage direct current (HVDC) transmission link, SuedLink plays a key role in the energy transition and the secure power supply of tomorrow.
In Lot 8, in the districts of Bad Kissingen, Main-Spessart and Würzburg, the conditions for secure and future-proof energy transmission are being created along a route length of around 71 km. High-performance protection pipes for high- and extra-high-voltage cables from egeplast are used to protect the power cables.

Efficient installation along long route sections
At around 61 km, the majority of the route was implemented using trenching. This creates a narrow trench into which the cable protection pipes are installed directly. The method offers advantages, especially along long route sections:
- surface disruption is minimized,
- excavated soil can be reused as backfill material,
- long pipe strings enable rapid construction progress.
This reduces both construction site areas and logistical effort. At the same time, trenching can also be used in more challenging soil conditions and supports the cost-effective implementation of major infrastructure projects. A further ten km of the project were implemented using horizontal directional drilling (HDD) to safely cross sensitive areas and existing infrastructure. The combination of open-cut and trenchless installation methods places high demands on material quality, load-bearing capacity, and logistics along the entire route.

High material requirements for increased thermal stability
The egeplast Power Protect PE-RT protection pipes used are based on a specially developed PE-HD material with increased thermal stability. The pipe systems are designed for the requirements of high- and extra-high-voltage cables and support the long-term value retention of power grids. They therefore make an important contribution to a permanently secure and future-proof energy infrastructure.

Contribution to the energy transition
Projects such as SuedLink demonstrate the importance of high-performance pipe systems for the energy transition. In future, the direct current link is intended to transport large quantities of renewable energy over long distances, thereby contributing to security of supply in Germany. With robust protection pipe solutions and installation-friendly systems, egeplast supports grid operators and construction companies in implementing demanding infrastructure projects for a sustainable energy supply.

Project Description
SuedLink Lot 8: Expansion of a 71 km HVDC route in Lower Franconia
Challenges
Combination of trenching and HDD crossings with high requirements for material and logistics
Solution
Use of egeplast Power Protect PE-RT cable protection pipes for high- and extra-high-voltage cables
Installation
approx. 61 km trenching, approx. 10 km HDD
Pipe System
egeplast Power Protect PE-RT
Project Participants
TransnetBW
egeplast
Power Protect PE-RT
Protective pipes for high and extra-high voltage cables with a low-friction inner layer and individual marking.
UV-resistant signal color layer
Solid wall or co-extruded, optionally with stripes
Inspection-friendly inner layer: optionally highly slidable or abrasion-resistant