Beneath an active campsite at Lake Balaton in Hungary, a DN 500 asbestos cement sewer pipeline was trenchlessly rehabilitated using the Close-Fit method. The confined space and limited access points made the project particularly challenging. By using the egeLiner® DN 500 in the Close-Fit method, the rehabilitation could be implemented on schedule and safely.

Challenge: Rehabilitation of a wastewater pipeline with limited access to the old pipe
Due to the location of the 398.3 m long pipeline to be rehabilitated beneath a campsite, conventional open-trench construction was ruled out. Several permanently installed mobile homes blocked potential access routes, meaning only very few and, above all, small excavation pits were feasible. Furthermore, Lake Balaton is a very popular tourist destination for visitors from all over Europe, which leaves only a very limited time window for maintenance and rehabilitation work outside the season.

Solution: Precise Application of the Trenchless Close-Fit Method with Minimal Construction Area Requirements
The installation of the egeLiner®‑pipes using the Close-Fit‑method was carried out by Bonex, a company specializing in trenchless installation. The pipe drums could only be positioned at two insertion pits. From there, five pre-deformed sections were successively pulled through several old pipe segments and, by reversion, laid against the inner wall of the old pipe. The confined space conditions in this project highlighted the significant advantages of the egeLiner® rehabilitation method. The reduced cross-section of the folded Inliner, the ability to make directional changes using bends, and the delivery of entire rehabilitation sections on drums enabled the necessary insertions without requiring welding in the starting area of the excavation pits.




Project Description
Rehabilitation of a 398.3 m DN 500 AC transport pipeline in Hungary
Challenges
Pipeline under developed area; therefore minimal access and very limited space for excavation pits
Solution
Insertion of five pre-deformed egeLiner® sections via two insertion pits; Close-Fit method
Installation
Trenchless; Close-Fit Lining
Pipe System
egeLiner®, DN 500, PE 100 RC, SDR 21
Project Participants
Client: DRV Zrt.
Planning: NODIG ’99 Kft.
Execution: BONEX Építőipari Kft.
egeplast
egeLiner®
The pre-shaped egeLiner® is wound onto steel drums, tailored to the length of the section being renovated. This achieves a cross-sectional reduction of up to 40 percent, allowing long construction lengths to be delivered to the site.
Fundamentally, the folded egeLiner® pipe strives to equalize the stresses frozen in its wall and transform back into its round original shape — this is referred to as the reversion process, which causes the return to the original form (“memory effect”). This property makes the close-fit method highly efficient and ensures that, after successful Installation, the egeLiner® adheres closely to the inner wall of the old pipe and can be fully integrated into the existing pipeline network without restriction.
Learn more



