With egeplast egeXXL through Rotterdam’s subsurface
The municipality of Rotterdam in the Netherlands is investing in the future of its wastewater infrastructure. To replace a wastewater pipeline that was around 100 years old, a new network connection was created. This was implemented via two horizontal directional drillings (HDD), each more than 1,000 m long. The egeXXL large-diameter pipe made of PE 100-RC was used.

High requirements for safety and quality
The existing wastewater pipeline had reached the end of its service life and was to be replaced by a future-proofed solution. Due to the required capacity, the municipality of Rotterdam opted for two separate horizontal directional drillings (HDD) with lengths of 1,032 m and 1,010 m. Around 2,200 m of egeXXL large-diameter pipe made of PE 100-RC with a diameter of 900 mm in SDR 11 was installed. Both routes were laid at a depth of around 40 m. The work was carried out in a challenging urban environment, with correspondingly high requirements for planning, logistics and execution.
In addition to the technical implementation, the focus was particularly on quality assurance. Comprehensive testing and inspection measures were defined in advance together with the municipality of Rotterdam.

© De Jongh Pipesystems
The municipality of Rotterdam is investing in the future of its wastewater infrastructure.

© De Jongh Pipesystems
The work was carried out in a challenging urban environment.
Logistical challenge throughout the entire project duration
Delivery of the pipes began in August 2025. In eight partial deliveries, they were transported by a total of 28 trucks to the interim storage facility of the logistics partner Zwatra in Delft.
In early 2026, they were transported onward to the construction site, where they were welded into two pipe strings, each around 1,000 m long. After assembly of the pre-assembled pipe strings, pressure tests were carried out before the actual pipe pull-in. The construction project was supplemented by 11 preFab fittings in OD 900 SDR 11 from De Jongh Pipe Systems BV, with a total of 44 welded joints.
© De Jongh Pipesystems
The two successful HDD drillings made it possible to create a high-performance new wastewater connection.
© De Jongh Pipesystems
The combination of high material quality and precisely coordinated project logistics enabled the safe implementation of this demanding infrastructure project.
Reliability for the next generations
The two successful HDD drillings made it possible to create a high-performance new wastewater connection without having to open up the surface over a large area. For the municipality of Rotterdam, this means a long-term modernisation of a central infrastructure component while minimising interventions in the urban environment.
The project demonstrates the contribution that egeplast egeXXL large-diameter pipe systems can make to the renewal of existing networks. The combination of high material quality and precisely coordinated project logistics enabled the safe implementation of this demanding infrastructure project.
In the final project evaluation with the municipality of Rotterdam, the cooperation of all parties involved was explicitly rated positively.
Project Description
Renewal of an old wastewater pipeline by constructing a new high-performance wastewater connection in Rotterdam (NL)
Challenges
Challenging urban environment and high requirements for quality assurance, logistics and execution
Solution
Trenchless horizontal directional drilling (HDD) for a long-term high-performance and future-proofed wastewater infrastructure
Installation
Two HDD drillings with lengths of 1,032 m and 1,010 m at a depth of around 40 m
Pipe System
egeplast egeXXL PE 100-RC, OD 900 mm, SDR 11
Project Participants
Municipality of Rotterdam (client), De Jongh Pipe Systems BV, Zwatra Logistics
egeplast
egeXXL Large-Diameter Pipe System
Large-diameter pipes up to 1,600 mm for a wide range of applications in new construction and rehabilitation
Secure, homogeneous connections through welding technology and a comprehensive range of fittings
Learn more