In southern Emsland, the expansion of the green electricity grid is entering a significant stage: By constructing a 12-km direct current connection from Wietmarschen to Lingen (Ems), Amprion will provide for a grid connection to BorWin 4 & DolWin 4 by 2028. The project makes use of the egeplast Power Protect PE-RT cable protection pipe system part of which was installed using the environmentally friendly HDD method.
The contractor commissioned to execute the construction project launched in summer 2024, Amprion Offshore GmbH is ARGE Tief4 BD4 LA Süd, consisting of Knoll GmbH & Co. KG, Bernhard Heckmann GmbH & Co. KG, Depenbrock Bau GmbH & Co. KG and Sonntag Baugesellschaft mbH & Co.KG. Amprion opted in favour of the egeplast Power Protect PE-RT cable protection pipe system featuring enhanced thermal stability for high- and extra-high voltage cables of up to 525 kV along with a number of different connection systems (double socket, electro fusion coupler, Golden Joint) and transistion fittings.
“Over the course of work preparation, egeplast was always at our disposal providing the technical expertise required to ensure a maximally efficient workflow.”
Sven Vaske, Site Supervision Knoll GmbH & Co. KG
Static calculations as a service
Owing to the soil conditions, open-trench installation was used over long distances. Some partial segments, however, could also be installed using the cost-efficient and environmentally friendly HDD method. A particularly complex section was the one crossing under the Dortmund-Ems Canal, the river Ems as well as traversing a Fauna- Flora-Habitat (FFH) area, a nature conservation and landscape protection area in the region of Lingen Hanekenfähr. Based on the calculated tractive force, the HDD-drilling across a length of approx. 1,100 m (6 strings) was shifted from SDR 11 to SDR 7.4. A particular challenge in this context consisted in pretensioning the pipes in the difficult-to-access forest terrain. Thus, comprehensive previous land clearing measures were required.
Apart from precise planning, complex drilling operations such as these in particular require good communication and cooperation between the contractor and the pipe manufacturer. Sven Vaske, the overall project manager from ARGE Tief4 LA Süd, arrived at a consistently positive assessment of the exchange between these parties: “Over the course of work preparation, egeplast was always at our disposal providing the technical expertise required to ensure a maximally efficient workflow”. Among the advisory services provided by egeplast were, among other items, the static calculations both for the construction and operating stages. As a result, the southern section is scheduled to be completed by December 2025.
egeplast
egeFit®
Connection technology Golden Joint
With increased thermal stability for high and extra-high voltage cables up to 525 kV |
UV-resistant signal colour layer |
Solid wall or coextruded, optionally with stripes |
Inspection-friendly inner layer: optionally low-friction or abrasion-resistant |
Project description | BorWin4/DolWin4 Southern section; route length 12 km; direct current connections from Wietmarschen to Lingen (Ems) |
Challenges | Preparation of cable protection pipe systems for extra-high voltage DC transmission (HVDC) |
Solution | Use of egeplast Power Protect PE-RT cable protection pipe system with enhanced thermal stability for high and extra-high voltage cable of up to 525 kV with different kinds of connection techniques (double socket, electrofusion socket, Golden Seam) and adaptors |
Installation | Open-trench construction (installation in a trench) & trenchless installation (HDD) |
Pipe system | 6,900 m egeplast Power Protect PE-RT 280 x 38.3 mm (12 m sticks) 7,800 m egeplast Power Protect PE-RT 280 x 25.4 mm (12 m sticks) 36,000 m egeplast Power Protect PE-RT 250 x 14.8 mm (15 m sticks) – 200 x PE-RT electro fusion coupler d 250 mm – 1,850 x double socket d 250 mm – 2 x egeFit® „Golden Joint“ connector 280 x 25.4 mm – 40 x transition fittings d 280 mm (SDR11) to d 250 mm (SDR17) – Additional accessories – Welding equipment (e.g. 2 welding units) |
Project participants | Client: Amprion GmbH Execution of construction work: ARGE Tief4 BD4 LA Süd (Knoll GmbH & Co. KG, Bernhard Heckmann GmbH & Co. KG, Depenbrock Bau GmbH & Co. KG und Sonntag Baugesellschaft mbH & Co. KG) |

Dipl.-Ing. Sven Vaske
E-Mail: sven.vaske@knoll-bau.de
Tel.: +49 151 1951 9677

Alexander Cosse
E-Mail: alexander.cosse@egeplast.de
Tel.: +49 176 14971 530